Thanks to the good industrial performance of France’s nuclear fleet, EDF revises higher its estimate nuclear power generation in France for 2024. Initially estimated between 315-345 TWh, nuclear power generation is now estimated between 340-360 TWh.
This higher nuclear power generation estimate is based on improved performance of outages and industrial control of stress corrosion inspections and repair work, and the absence of major climatic event during summer.
The Group has implemented the START 2025 action plan aimed at improving the operational efficiency of outages, since 2019. It covers various areas: industrialisation, capitalisation, and standardisation of outages preparation methods, a refined strategy for allocating resources and skills, including the setting up of pooled teams and more employee training in sensitive actions.
Since early 2024, eleven reactors have been reconnected to the grid before the scheduled date.